Hello sh.itjust.works community,

Many of you have been eager to get an update about when the sh.itjust.works instance will get it’s upgrade to the latest version of lemmy. Here’s a update along with a tentative timeline.

In December 2023 I purchased a new server for this community. It took me awhile but I eventually made the time to get it racked at the local datacenter. For the sysadmins lingering and those interested here are the specs:

  • Dual Xeon 2.9Ghz CPUs (32 cores total)
  • 256GB ram
  • 4 x 1TB SSD in raid 10 (with room to add 6 more disks)
  • 10gbit networking

While I’m ready to proceed with the upgrade, I’ve decided to first migrate this instance over to the new hardware. Here are two reasons.

  1. Those of you who have been around long enough may remember that I’ve been running this instance on “borrowed” unused resources that were available at the time. There are no more resources available for this instance to grow.
  2. There are reports that the latest version of lemmy may use more resources. Given we are among the bigger instances, should I end up in a situation where I need to increase resources to keep things fast I’ll be restricted.

Here’s the tentative timeline:

Task Date Expected Downtime
Migration to new server Tuesday February 27 2024 @ 8:00PM ET 90 Minutes
Upgrade to V19.3 Thursday February 29 2024 @ 8:00PM ET Up to 120 Minutes
  • If anything major goes wrong on the 27th I will revert back the changes and bring the instance back up on the current server.
  • If anything major goes wrong on the 29th I will revert back using an earlier snapshot. If that fails, I will restore from a backup.

During these two planned events those who want to provide moral support or who want to get periodic updates are more than welcome to join us on our matrix channel